Issue of a decision for conduction the complex works on the objects (demolition of buildings and structures) post-utilization
Legal person
Natural person
Individual businessman
Government body
Local executive bodies
Cost of services
Issued free of charge
Term of services
Simple objects 5 (five) working days
Difficult objects 10 (ten) working days
The name of service according to RPS
Issue of a decision for conduction the complex works on the objects (demolition of buildings and structures) post-utilization
Documents for downloading
Normative legal acts
An authorization needed to get the public service
To apply for the following documents are required
For legal entities
For individuals
For individual entrepreneurs
For individuals
For individual entrepreneurs
For legal entities
- A copy of the expert opinion on technical survey of reliability and stability of buildings and structures issued by an expert with the corresponding certificate for the right to carry out technical survey of reliability and stability of buildings and structures, or an accredited organization with certified experts (necessarily )
- In case of demolition of the facility by contract, an electronic copy of the contract contract is provided (optional , job specifications )
- If the property has several owners, then it is necessary to provide an electronic copy of the notarized written consent of other owners of the object to carry out a complex of post-disposal works (demolition of buildings) and its parameters (optional , job specifications )
- If the complex of demolition works affects the interests of adjacent owners of premises (parts of the house), then it is necessary to provide an electronic copy of notarized written consent of adjacent owners of premises (parts of the house) (optional , job specifications )
- Electronic copy of the PPR (not required for facilities specified in article 74, paragraph 1, of the Law of the Republic of Kazakhstan dated July 16, 2001 "On architectural, urban planning and construction activities in the Republic of Kazakhstan" )/project (project and estimate) documentation (optional , job specifications )
- In case of recognition of an apartment building as emergency, an electronic copy of the relevant conclusion on the demolition of the interdepartmental commission created by the local executive body in accordance with Appendix A of the Methodological Recommendation on the demolition of emergency apartment buildings approved by order of the Chairman of the Agency for Construction and Housing and Communal Services of December 29, 2012 No. 795 (optional , job specifications )
- Application in form according to Annex 3 to this Regulation certified by the EDS of the service recipient (optional , job specifications )(Data form)
For individuals
- A copy of the expert opinion on technical survey of reliability and stability of buildings and structures issued by an expert with the corresponding certificate for the right to carry out technical survey of reliability and stability of buildings and structures, or an accredited organization with certified experts (necessarily )
- In case of demolition of the facility by contract, an electronic copy of the contract contract is provided (optional , job specifications )
- If the property has several owners, then it is necessary to provide an electronic copy of the notarized written consent of other owners of the object to carry out a complex of post-disposal works (demolition of buildings) and its parameters (optional , job specifications )
- If the complex of demolition works affects the interests of adjacent owners of premises (parts of the house), then it is necessary to provide an electronic copy of notarized written consent of adjacent owners of premises (parts of the house) (optional , job specifications )
- Electronic copy of the PPR (not required for facilities specified in article 74, paragraph 1, of the Law of the Republic of Kazakhstan dated July 16, 2001 "On architectural, urban planning and construction activities in the Republic of Kazakhstan" )/project (project and estimate) documentation (optional , job specifications )
- In case of recognition of an apartment building as emergency, an electronic copy of the relevant conclusion on the demolition of the interdepartmental commission created by the local executive body in accordance with Appendix A of the Methodological Recommendation on the demolition of emergency apartment buildings approved by order of the Chairman of the Agency for Construction and Housing and Communal Services of December 29, 2012 No. 795 (optional , job specifications )
- Application in form according to Annex 3 to this Regulation certified by the EDS of the service recipient (optional , job specifications )(Data form)
For individual entrepreneurs
- A copy of the expert opinion on technical survey of reliability and stability of buildings and structures issued by an expert with the corresponding certificate for the right to carry out technical survey of reliability and stability of buildings and structures, or an accredited organization with certified experts (necessarily )
- In case of demolition of the facility by contract, an electronic copy of the contract contract is provided (optional , job specifications )
- If the property has several owners, then it is necessary to provide an electronic copy of the notarized written consent of other owners of the object to carry out a complex of post-disposal works (demolition of buildings) and its parameters (optional , job specifications )
- If the complex of demolition works affects the interests of adjacent owners of premises (parts of the house), then it is necessary to provide an electronic copy of notarized written consent of adjacent owners of premises (parts of the house) (optional , job specifications )
- Electronic copy of the PPR (not required for facilities specified in article 74, paragraph 1, of the Law of the Republic of Kazakhstan dated July 16, 2001 "On architectural, urban planning and construction activities in the Republic of Kazakhstan" )/project (project and estimate) documentation (optional , job specifications )
- In case of recognition of an apartment building as emergency, an electronic copy of the relevant conclusion on the demolition of the interdepartmental commission created by the local executive body in accordance with Appendix A of the Methodological Recommendation on the demolition of emergency apartment buildings approved by order of the Chairman of the Agency for Construction and Housing and Communal Services of December 29, 2012 No. 795 (optional , job specifications )
- Application in form according to Annex 3 to this Regulation certified by the EDS of the service recipient (optional , job specifications )(Data form)